Forecasting

Predicting when work will be done using real delivery data, expressed as ranges rather than single dates.

2 min read · Practitioner

In 30 seconds

  • Forecasts use what the team actually finishes, not hopes.
  • Always give a range, ideally with a confidence level.
  • Update the forecast every sprint as data comes in.

Three common methods

MethodHow
Velocity rangeRemaining points divided by lowest and highest recent velocity
ThroughputRemaining items divided by items finished per week
Monte CarloSimulate thousands of futures from past throughput; read off 50% and 85% dates

A quick example

120 points remain. Recent velocity ranges from 20 to 30 per sprint. Forecast: 4 to 6 sprints. Stakeholders hear a range they can plan around, not a single date that will probably slip.

Communicating it

  • State the range and how confident you are
  • Show what would move it, such as scope added
  • Re-forecast every sprint, as the cone of uncertainty narrows

Myth vs reality

Myth · Forecasts are commitments.
Reality · A forecast is a best estimate; it changes with new data.
Myth · You need story points to forecast.
Reality · Item throughput often forecasts just as well.
Myth · Monte Carlo is too complex.
Reality · Free spreadsheets and tools make it a few minutes' work.

The AI angle

After a team adopts AI tools, its delivery history stops being a reliable guide. Re-baseline with a few sprints of new data and forecast in ranges until the pattern settles.

Estimation and Velocity with AI →

FAQ

How much history do we need?

Even three to five sprints or a few weeks of throughput helps.

What confidence level should we quote?

85% is a common choice for planning commitments.

How do we handle added scope?

Track it separately so its effect on the date is visible.