Burndown vs Burnup Chart

Show what's left, or show what's done against total scope? How the two charts differ and when to use each.

2 min read · Beginner

In 30 seconds

  • Burndown: one line of remaining work falling to zero.
  • Burnup: two lines, completed work rising toward total scope.
  • Burnup makes scope changes visible; burndown hides them.

Pick a burndown when…

  • Tracking a single sprint with stable scope
  • The team wants a simple daily check

Pick a burnup when…

  • Tracking a release over many sprints
  • Scope changes and you need stakeholders to see it
  • Forecasting a finish date from progress

Side by side

BurndownBurnup
LinesRemaining workCompleted work and total scope
Scope addedLooks like no progressScope line rises visibly
Best horizonOne sprintRelease or project
Ease of readingVery simpleSlightly more to explain

Myth vs reality

Myth · Burnup charts are just upside-down burndowns.
Reality · Burnups show scope as a separate line.
Myth · You must pick one.
Reality · Many teams use burndown for sprints and burnup for releases.
Myth · Charts measure productivity.
Reality · They show progress against a plan.

FAQ

What units do these charts use?

Story points, item count or task hours.

Do tools draw both?

Most agile tools offer both.

Which do executives prefer?

Usually burnup, because scope changes are visible.