Velocity vs Throughput

Points per sprint, or items per week? Two ways to measure delivery rate, and which forecasts better.

2 min read · Practitioner

In 30 seconds

  • Velocity sums story points finished per sprint.
  • Throughput counts items finished per time period.
  • If items are similar in size, throughput forecasts just as well with less effort.

Pick velocity when…

  • The team already estimates in story points
  • Items vary a lot in size
  • The team works in fixed sprints

Pick throughput when…

  • Items are split to similar, small sizes
  • The team uses Kanban or continuous flow
  • You want to skip estimation overhead

Side by side

VelocityThroughput
UnitStory points per sprintItems per week
Needs estimatesYesNo
Typical methodScrumKanban
ForecastingPoints left / velocity rangeItems left / throughput, or Monte Carlo

Myth vs reality

Myth · Throughput ignores item size.
Reality · It relies on keeping items similar in size.
Myth · Velocity is more precise.
Reality · Both give ranges; precision is an illusion.
Myth · You can't use throughput in Scrum.
Reality · Many Scrum teams do.

FAQ

Can we track both?

Yes; comparing them can reveal estimation drift.

Which works for Monte Carlo forecasting?

Throughput is the usual input.

Should we compare teams on either?

No; both are for a team's own planning.