The share of total lead time that work is actively being worked on, rather than waiting.

2 min read · Practitioner

In 30 seconds

  • Active time divided by total lead time.
  • Many teams find work waits most of the time.
  • Improve it by cutting waits, not by working faster.

How it's calculated

Flow efficiency = active work time / total lead time x 100

An item worked on for 2 days that took 10 days end to end has 20% flow efficiency.

What teams usually find

When teams first measure it, flow efficiency is often low: work spends far more time waiting for reviews, approvals, testing or handoffs than being worked on. Value stream mapping shows exactly where.

Improving it

Myth vs reality

Myth · Low flow efficiency means people are slow.
Reality · It means work is waiting.
Myth · 100% is the goal.
Reality · Some waiting is normal; aim to improve the trend.
Myth · Working harder improves it.
Reality · Cutting wait time does.

FAQ

How do we measure active time?

Track when items are in active versus waiting states on the board.

Is this the same as resource utilization?

No; high utilization often lowers flow efficiency.

Which waits should we tackle first?

The longest ones on the value stream map.