Burnup Chart

A chart with two lines, work completed and total scope, that shows progress and scope changes clearly.

2 min read · Practitioner

In 30 seconds

  • One line for work done, one for total scope.
  • Scope changes show up as the scope line moving.
  • Ideal for release tracking and forecasting.

Try it

CompletedScopeForecast range

How to read it

The x-axis is time (days or sprints). The completed line rises as work finishes. The scope line shows total planned work. Where the lines meet is when the work is done.

Patterns

PatternMeans
Scope line risingWork is being added
Completed line flatNothing is finishing
Lines converging steadilyOn track

Forecasting

Extend the completed line using best and worst recent velocity to show a range for where it meets scope. That gives an honest date range. See burndown vs burnup.

Myth vs reality

Myth · A burnup is just an upside-down burndown.
Reality · It adds the scope line, which changes the story.
Myth · Rising scope is always bad.
Reality · It may reflect learning; the chart just makes it visible.
Myth · Burnups are only for Scrum.
Reality · Kanban teams use them with item counts.

FAQ

What units should we use?

Story points or item counts.

Should scope ever go down?

Yes, when items are removed; show that too.

Who should see the chart?

The team and stakeholders.