In 30 seconds
- Counts finished items per week or sprint.
- No estimates needed; just count.
- The main input for flow-based forecasting.
Try it
Monte Carlo forecast: 10,000 simulated futures, each week drawn at random from your history. Plan commitments around the 85% figure.
How to measure it
Count items reaching "done" each week. Track it over time; a run chart shows the range and stability. Throughput works best when items are split to similar, small sizes.
Forecasting
Divide remaining items by throughput to get a range, or use Monte Carlo simulation on past weekly throughput for a probability-based date. See forecasting and velocity vs throughput.
Little's Law
Average lead time = average work in progress / average throughput. Raising throughput or lowering WIP shortens lead time.
Myth vs reality
The AI angle
Throughput counts finished items, which makes it more robust than story points when AI changes effort. Keep items small and similar so the count stays meaningful.
FAQ
What counts as an item?
Whatever the team finishes: stories, bugs, tasks. Be consistent.
Should bugs count?
Track them separately or together, but consistently.
How much history do we need?
A few weeks to start; more improves forecasts.